CSM-001 Exam Questions Get Updated [2022] with Correct Answers [Q21-Q41]




CSM-001 Exam Questions Get Updated [2022] with Correct Answers

Practice CSM-001 Questions With Certification guide Q&A from Training Expert ExamsLabs


How much CSM-001 Exam Cost

The price of the CSM-001 exam is $128 USD.

 

NO.21 Please select which statement is the most accurate:

 
 
 
 

NO.22 The Sprint Backlog is owned by?

 
 
 
 

NO.23 True or False: The sprint planning is a one-day time boxed meeting divided into two 4-hour sessions?

 
 

NO.24 The term Agile Development was first introduced in.

 
 
 
 

NO.25 The correct sequence of events in using Scrum framework is as follows:

 
 
 
 

NO.26 Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

 
 
 
 

NO.27 According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time?

 
 
 
 

NO.28 A line in the Agile Manifesto reads, “____________ and _____________ over processes and tools”.
Please select which option best completes the statement.

 
 
 
 

NO.29 Which three questions are answered by all Development Team members at the Daily Scrum? (Choose three)

 
 
 
 
 

NO.30 Development Team members volunteer to own a Sprint Backlog item:

 
 
 
 

NO.31 As the Sprint planning progresses, the workload has grown beyond the development team’s capacity. Which action makes most sense for the Team?

 
 
 
 

NO.32 When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

 
 
 
 

NO.33 Which of the following questions is not relevant for regular Scrum Meeting?

 
 
 
 

NO.34 Which statement best describes what it means for an activity to be time-boxed?

 
 
 
 

NO.35 Which statement best describes Scrum?

 
 
 
 

NO.36 You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?

 
 
 
 

NO.37 Upon what type of process control is Scrum based?

 
 
 
 

NO.38 ________________ constitute the Sprint Backlog and are often estimated in hours?

 
 
 
 

NO.39 Which of the following questions is not relevant for regular Scrum Meeting?

 
 
 
 

NO.40 The term Agile Development was first introduced in:

 
 
 
 

NO.41 What is the Scrum?

 
 
 
 

Prepare Top GAQM CSM-001 Exam Audio Study Guide Practice Questions Edition: https://www.examslabs.com/GAQM/GAQM-certification/best-CSM-001-exam-dumps.html 1

Links:
  1. https://www.examslabs.com/GAQM/GAQM-certification/ best-CSM-001-exam-dumps.html
Post date: 2022-06-17 09:55:18
Post date GMT: 2022-06-17 09:55:18

Post modified date: 2022-06-17 09:55:18