This page was exported from Exams Labs Braindumps [ http://blog.examslabs.com ] Export date:Wed Nov 27 6:54:00 2024 / +0000 GMT ___________________________________________________ Title: [Apr-2023] C-TS422-2021 Certification with Actual Questions from ExamsLabs [Q33-Q56] --------------------------------------------------- [Apr-2023] C-TS422-2021 Certification with Actual Questions from ExamsLabs Updated C-TS422-2021 Dumps PDF - C-TS422-2021 Real Valid Brain Dumps With 82 Questions! Q33. Your proyect team decides to use a make-to-order planning strategy for strategic in discrete manufacturing.What is the impact of this decision?  Net requirement calcualtion is sales-order specific.  A sales-order-specific planning run is required.  Storage location MRP areas are required.  Production orders specific stock is created Q34. What is a work center hierarchy in planning in SAP S/4HANA?  A group of alternative work centers providing a cumulative available capacity for production.  A group of alternative work centers for production, structured in hierarchy levels by priorities  A group of work centers in a production line being used in sequence for production  A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel Q35. For which categories can you define BOMs in SAP S/4HANA?  Work Center  Sales order  Class  Document Structure Q36. What are the consequences when you assgn a planned order to a production line manually, using the planning table in repetitive manufacturing?  The planed order’s component availability is checked.  The planed order is converted to production order.  The planned order’s components are copied to the picking list.  The planed order generates capacity requirements Q37. Which standard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.  Non-stock item  Work item  Variable-size item  WBS item Q38. During production order creation, several valid production versions are found. How does the system choose the production version?  Planned order or material number  Valid period or sale order  Alphanumeric or quota arrangement  Lot size or material cost Q39. Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA?  First in first out (FIFO)  100% check  Simultaneous  By usage probability Q40. If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?  Fill up based on the lot size procedure  Fill up to the maximum stock level  Fill up to the safety stoc level  Fill up to the reorder stock level Q41. What happens to this dependent requirement when you convert the planned order into a production order?  They are converted into a schedule line.  They are converted into a reservation.  They are converted into a production order.  They are converted into a planned order. Q42. What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?  Material Requirements Planning (MRP)  Capacity Requirements Planning (CRP)  Supply Network Planning (SNP)  Demand Planning (DP) Q43. The MRP run detected a shortage of a materila that you sorce from an external supplier in full pallets. How can you make sure you will only recive full pallets?  Use the fixed lot procedure.  Use the MRP type for vendor managed inventory.  Use the minimum order quantity  Use the reorder point Q44. Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?  When multiple operations are maintained for one product  When alternate resources are used within one operation  When multiple planned orders exist on one resource  When multiple production versions are maintained for one product Q45. Which SAP solutions support the supplier area in the portfolio of the Digital Value Network?  SAP Ariba  SAP Hybris  SAP Concur  SAP Fieldglass  SAP SuccessFactors Q46. Advanced Planning uses master data and transaction data from SAP S/4HANA. In which data objects can you set the advanced planning flag?  Work center  Production version  Plant  Material Q47. An issue storage location was NOT found through the work center, bill of material(BOM) item, or material master. What determines whether the storage location can be derived from the production version?  MRP group  Plants parameters  MRP controller  MRP profile Q48. When can the automatic material availability check occur in a production order?  At order release  At order confirmation  At order creation  At order settlement Q49. Which time elements are part of a routing operation?  Pick/pack time  Float before production  Queue time  Wait time  Move time Q50. Which of the following are possible configuration steps when setting up the alert monitor in Advance Planning?  Create object selection variant for transportation lane-related alerts.  Create object selection variant for product-related alerts.  Assign the overall profile to the authorization profile.  Assign the alert profile to the overall profile. Q51. You want to schedule an operation finitely, without moving other operations. Which scheduing strategy do you select?  Schedule in working time only  Squeeze in  Insert operation  Find slot Q52. Which SAP application can be used for forcasting in Supply Chain Planning?  Material Requirements Planning (MRP)  Supply Chain Management(SCM)  Integrated Business Planning (IBP)  Capacity Requirements Planning (CRP) Q53. How can you carry out cost object controlling for production orders?  Milestone-related  Cost-related  Product-related  Order-related Q54. How can you set up the supply source for the Kanban process in SAP S/4HANA?  Using run schedule quantities for in-house production  Using quotations for internal and external procurement  Using purchase orders for external procurement  Using stock transfer reservations for stock transfer  Using purchasing costs for automated source prioritization Q55. What are some uses for the low-level code assigned to each material?  It is used in MRP to determine the sequence in which materials are planned.  It is used by product costing to determine how coast are rolled up.  It is used by engineering to indentify subitems in an engineering bill of material (BOM).  it is used by ATP to determine the priority of alternative components. Q56. What does a line hierarchy in repetitive manufacturing represent?  A production line with a parallel sequence in the routing  A production line with prioritized alternative work centers  A production line with more than one work center  A production line with an alternative sequence in the routing  Loading … Pass Your C-TS422-2021 Exam Easily With 100% Exam Passing Guarantee: https://www.examslabs.com/SAP/SAP-Certified-Application-Associate/best-C-TS422-2021-exam-dumps.html --------------------------------------------------- Images: https://blog.examslabs.com/wp-content/plugins/watu/loading.gif https://blog.examslabs.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2023-04-20 14:30:48 Post date GMT: 2023-04-20 14:30:48 Post modified date: 2023-04-20 14:30:48 Post modified date GMT: 2023-04-20 14:30:48