Exams Labs Braindumps
https://blog.examslabs.com/2023/08/pass-your-pmi-pmi-rmp-exam-with-correct-117-questions-and-answers-q15-q32/
Export date: Thu Nov 21 13:23:28 2024 / +0000 GMT

Pass Your PMI PMI-RMP Exam with Correct 117 Questions and Answers [Q15-Q32]




Pass Your PMI PMI-RMP Exam with Correct 117 Questions and Answers

Latest [Aug 17, 2023] 2023 Realistic Verified PMI-RMP Dumps

QUESTION 15
You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.

 
 
 
 

QUESTION 16
You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete – though the project should be 49 percent complete. The project has spent
$455,897 to reach the 45 percent complete milestone. What is the project’s cost performance index?

 
 
 
 

QUESTION 17
Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of a response strategy is this?

 
 
 
 

QUESTION 18
A project manager wants to represent the distribution of uncertainty around a risk model element. However, good data on the variability, of the risk model element has not been collected, and only contains minimum and maximum values.
What curve should the project manager use to represent the distribution?

 
 
 
 

QUESTION 19
The risk manager for a data center infrastructure project performs a risk audit. Which of the following represents the primary goals of the audit?

 
 
 
 

QUESTION 20
SIMULATION
Fill in the blank with an appropriate phrase.
________are activities that are dangerous to complete and manage such as construction, electrical work, or manufacturing.

QUESTION 21
You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders’ approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?

 
 
 
 

QUESTION 22
You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?

 
 
 
 

QUESTION 23
A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.
What should the risk manager do with this risk?

 
 
 
 

QUESTION 24
You are the project manager of the NGH project for your organization. You want to create a causeand- effect diagram to help discover the root causes of the risks within the project. Harold, the CIO, recommends that you create an Ishikawa diagram instead. What is an Ishikawa diagram?

 
 
 
 

QUESTION 25
Your organization, as part of its enterprise environmental factors, has established risk governance to be implemented in each project. Part of this governance is the reassessment of risks within each project. How much detail and repetition in approach for risks to be reassessed for probability and impact?

 
 
 
 

QUESTION 26
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

 
 
 
 

QUESTION 27
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?

 
 
 
 

QUESTION 28
Sensitivity analysis is a technique for systematically changing parameters in a model to determine the effects of such changes and is useful for computer modelers for a range of purposes. Which of the following purposes does the sensitivity analysis include? Each correct answer represents a
complete solution. Choose all that apply.

 
 
 
 

QUESTION 29
A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.
What should the project manager do next?

 
 
 
 

QUESTION 30
You are the project manager of QSL project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?

 
 
 
 

QUESTION 31
Frank is the project manager of the NHL Project for his company and he is starting the risk identification process for the project. Frank needs to ensure that the correct stakeholders are interviewed as part of risk identification. What document will help Frank to communicate and solicit inputs of the project stakeholders during risk identification?

 
 
 
 

QUESTION 32
Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the following statements best defines what quantitative risk analysis will review?

 
 
 
 

Get 2023 Updated Free PMI PMI-RMP Exam Questions and Answer: https://www.examslabs.com/PMI/Project-Management-Professional/best-PMI-RMP-exam-dumps.html 1

Links:
  1. https://www.examslabs.com/PMI/Project-Management-P rofessional/best-PMI-RMP-exam-dumps.html
Post date: 2023-08-17 15:56:30
Post date GMT: 2023-08-17 15:56:30

Post modified date: 2023-08-17 15:56:30
Post modified date GMT: 2023-08-17 15:56:30

Export date: Thu Nov 21 13:23:28 2024 / +0000 GMT
This page was exported from Exams Labs Braindumps [ http://blog.examslabs.com ]